<rt id="qcweg"><center id="qcweg"></center></rt>
<rt id="qcweg"></rt><acronym id="qcweg"></acronym>
歡迎來到濱州恒通電力器材有限公司網站,我們竭誠為您服務

行業新聞
當前位置:首頁-資訊中心>行業新聞燃氣管道警示帶的作用

燃氣管道警示帶的作用

來源:http://www.sunk-enjoy.com/ 發布時間:日期:2024-03-25 0

1、當開挖施工時,如挖到燃氣警示帶,則表示在下方0.30.5米處有燃氣管道,起到了警示和保護作用。2、示蹤作用。尋找地埋燃氣管道時,找到警示帶即找到了管道,起到了示蹤作用。3、現在的警示帶有示蹤線,利用測試儀器在不開挖的情況下,準確為管道定位。

1. When excavating, if a gas warning tape is dug, it indicates that there is a gas pipeline located 0.3 to 0.5 meters below, which serves as a warning and protection. 2. Tracing effect. When searching for buried gas pipelines, finding the warning tape indicates that the pipeline has been found, playing a tracing role. 3. The current warning is equipped with a tracer line, which uses testing instruments to accurately locate the pipeline without excavation.

燃氣管道警示帶埋設要點

Key points for burying warning tapes for gas pipelines

1.溝槽開挖。

1. Trench excavation.

(1)混凝土路面和瀝青路面的開挖應使用切割機切割。

(1) The excavation of concrete pavement and asphalt pavement should be done using a cutting machine.

(2)管道溝槽應按設計規定的平面位置和標高開挖。當采用人工開挖且無地下水時,槽底預留值應為0.05~0.10m;管道安裝前應人工清底設計標高。

(2) The pipeline trench should be excavated according to the plane position and elevation specified in the design. When manual excavation is used and there is no groundwater, the reserved value at the bottom of the trench should be 0.05-0.10m; Before pipeline installation, the bottom should be manually cleaned to the design elevation.

(3)管溝溝底寬度和工作尺寸,應根據現場實際情況和管道敷設方法確定。

(3) The width and working dimensions of the trench bottom should be determined based on the actual site conditions and pipeline laying methods.

(4)局部超挖部分應回填夯實。當溝底無地下水時,超挖在0.15m以內,可采用原土回填;超挖在0.15,以上,可采用石灰土處理。當溝底有地下水或水量較大時,應采用級配砂石或天然砂回填標高。超挖部分回填后壓實,其密實度應接近原地基天然土的密實度。

(4) Partial over excavation should be backfilled and compacted. When there is no groundwater at the bottom of the ditch, if the over excavation is within 0.15m, the original soil can be used for backfilling; If the over excavation is above 0.15, lime soil treatment can be used. When there is groundwater or a large amount of water at the bottom of the ditch, graded sand or natural sand should be used to backfill to the elevation. After backfilling the over excavated part, the compactness should be close to the compactness of the natural soil in the original foundation.

(5)在濕陷性黃土地區,不宜在雨期施工,或在施工時切實排除溝內積水,開挖時應在溝底預留值0.03~0.06m厚的土層進行壓實處理。

(5) In areas with collapsible loess, it is not advisable to carry out construction during rainy periods or to effectively drain the accumulated water in the ditch. During excavation, a soil layer with a thickness of 0.03-0.06m should be reserved at the bottom of the ditch for compaction treatment.

20230511083918625.jpg

(6)溝底遇有廢棄構筑物、硬石、木頭、垃圾等雜物時必須,并應鋪一層厚度不小于0.15m砂土或素土,整平壓實及設計標高。

(6) When encountering abandoned structures, hard stones, wood, garbage and other debris at the bottom of the ditch, they must be removed, and a layer of sand or plain soil with a thickness of no less than 0.15m should be laid, leveled and compacted to the design elevation.

(7)對軟土基及特殊腐蝕土壤,應按設計要求處理。

(7) Soft soil foundation and special corrosive soil should be treated according to design requirements.

2.回填土。

2. Backfill soil.

(1)不得采用凍土、垃圾、木材及軟性物質回填。管道兩側及管頂以上0.5m內的回填土,不得含有碎石、磚塊等雜物,且不得采用灰土回填。距管頂0.5m以上的回填土中的石塊不得多于10%、直徑不得大于0.1m,且均勻分布。

(1) Frozen soil, garbage, wood, and soft materials shall not be used for backfilling. The backfill soil on both sides of the pipeline and within 0.5m above the top of the pipeline shall not contain debris such as crushed stones and bricks, and shall not be filled with gray soil. The number of stones in the backfill soil at a distance of more than 0.5m from the top of the pipe shall not exceed 10%, and the diameter shall not exceed 0.1m, and shall be evenly distributed.

(2)溝槽的支撐應在管道兩側及管頂以上0.5m回填完畢并壓實后,在保證的情況下進行拆除,并應采取細砂填實縫隙。

(2) The support of the trench should be backfilled and compacted on both sides of the pipeline and 0.5m above the top of the pipeline, and then removed while ensuring safety. Fine sand should be used to fill the gaps.

(3.)溝槽回填時,應先回填管底懸空部位,再回填管道兩側。

(3.) When backfilling the trench, the suspended area at the bottom of the pipe should be backfilled first, and then both sides of the pipe should be backfilled.

(4)回填土應分層壓實,每層虛鋪厚度宜為0.2~0.3m,管道兩側及管頂以上0.5m內的回填土必須采用人工壓實,管頂0.5m以上的回填土可采用小型機械壓實,每層虛鋪厚度宜為0.25~0.4m。

(4) Backfill soil should be compacted in layers, with a virtual paving thickness of 0.2-0.3m for each layer. Backfill soil on both sides of the pipeline and within 0.5m above the pipe top must be manually compacted. Backfill soil above 0.5m above the pipe top can be compacted using small machinery, and the virtual paving thickness for each layer should be 0.25-0.4m.

(5)回填土壓實后,應分層檢查密實度,并做好回填記錄。

(5) After the backfilling soil is compacted, the compactness should be checked layer by layer and backfilling records should be kept.

3.警示帶鋪設。

3. Lay warning tape.

(1)埋設燃氣管道的沿線應連續鋪設警示帶。警示帶鋪設前應將鋪設面壓實,并平整的鋪設在管道的正上方,距管定的距離宜為0.3~0.5m,但不得鋪設于路基和路面內。

(1) Warning tapes should be continuously laid along the buried gas pipeline. Before laying the warning tape, the surface should be compacted and laid flat above the pipeline. The distance from the pipeline should be 0.3-0.5 meters, but it should not be laid in the roadbed or road surface.

(2)警示帶宜采用黃色聚乙烯等不易分解的材料,并印有明顯、牢固的警示語,字體不應小于100*100mm。

(2) The warning tape should be made of materials such as yellow polyethylene that are not easily decomposed, and should be printed with clear and firm warning messages. The font should not be less than 100 * 100mm.

本文由供水警示帶提供技術支持,更多的詳細精彩內容請點擊我們的網站http://www.sunk-enjoy.com,我們將會全心全意為您提供滿意的服務。

This article is supported by water supply warning tapes. For more detailed and exciting content, please click on our website http://www.sunk-enjoy.com We will wholeheartedly provide you with satisfactory service.

相關產品 / Related products

  • 地釘

    地釘

  • 地釘

    地釘

  • 警示樁

    警示樁

  • 警示樁

    警示樁

截屏,微信識別二維碼

RM新时代入口-首页
<rt id="qcweg"><center id="qcweg"></center></rt>
<rt id="qcweg"></rt><acronym id="qcweg"></acronym>
RM新时代是骗人的吗 RM新时代网站 RM新时代|投资官网
<rt id="qcweg"><center id="qcweg"></center></rt>
<rt id="qcweg"></rt><acronym id="qcweg"></acronym>
rm海淘网官网入口 RM新时代赚钱项目 RM新时代app官方版下载 RM新时代还能玩多久 rm棋牌